Caroline Street Utility Project

Project Update: August 18, 2017





This week the contractor worked on installing the sanitary main up to E Main St. as well as the sewer and water services along the entire project to the south. The contractor has also completed the installation of the storm sewer.

Next week they will be extending the sanitary sewer and water main into E Main St. to make the final connections and finish the remaining service laterals on the northern end of the project. They will also be removing the old roadway and beginning the necessary repairs to the curb and gutter and sidewalks.

The concrete work is being coordinated with La Casa de Esperanza since they will also have contractors in to complete their curb and gutter and sidewalk work associated with their project.

Caroline Street is closed to through traffic between Arcadian Ave and Main Street; however, access will be maintained to the properties.


Project Contact:

Christopher J Langemak, P.E.
City of Waukesha - Engineering Division
262.524.3598 - Office
262.349.6512 - Mobile