Jefferson Ave, Oscar St. and Neighborhood Project

Project Update August 18, 2017


     

 

 

 

This project involves upsizing the existing sanitary sewer from near the intersection of Jefferson & Oscar to the intersection of Greenway Terrace & Manhattan. In addition, the sanitary sewer will be lined from the intersection of Greenway Terrace & Manhattan to the intersection of Butler & Jennifer. Rerouting of a sanitary force main in the intersection of Butler Dr and Rustic Way will also be necessary. The Water Utility will also replace several water services on Oscar St. Disturbed pavement areas will be restored with new pavement curb to curb.

This week, the contractor completed the mainline sanitary sewer installation on Greenway Terrace. The sewer on Butler between Greenway Terrace and Jennifer as well as a section of sewer on Greenway Terrace between Manhattan and Butler was also lined. Work began on removing the curb ramps on the street corners.

Next week the contractor will complete one remaining lateral connection on Greenway Terrace and then move over to the intersection of Butler Dr and Rustic Way to complete the force main tie over. The lining of the sanitary sewer on Greenway Terrace between Manhattan and Butler will be finished. Curb ramp removal and replacements will continue throughout the project

 

  
Pre-Construction Package sent out to Residents
    
Project Contact Information:
Jonathan Schapekahm, P.E.
262-524-3584