Project Update August 11, 2017
  

  

 

This week the City’s contractor finished paving all of the asphalt at Lemira Avenue, Prospect Avenue, and Bidwell Avenue. The reminder of this week the plan on finish grading the terrace, and begin installing the sod.

Next week they plan on finishing all of the sod work within the project limits.


  

 

 