Proposed Fire Station No. 3 and Police Substation and Sanitary Sewer Extension

Project Update: August 18, 2017

    

 

 

Building

:
The contractor received the second delivery of trusses for the living quarter portion of the project.  The interior masonry walls are complete.  Interior stud wall framing has begun.


River Valley Rd Sanitary Extension and Access Rd to Building

:
This week the contractor completed installing erosion control and removed the topsoil along the easement from River Valley Rd to Les Paul Pkwy (Hwy 59) in preparation for the sanitary sewer.

Next week they are scheduled to begin work on the installation of the sanitary sewer.

picture 2
The Westerly drive into the church has been closed to church traffic and is being used for construction traffic. 


Contact Information:
Building:
Katie Jelacic, P.E.
Project Engineer
262-524-3587
262-349-6511 (c)
kjelacic@waukesha-wi.gov

Sewer Extension:
Chris Langemak, P.E.
Project Engineer
262-524-3598
262-349-6512 (c)

picture 3