Proposed Fire Station No. 3 and Police Substation and Sanitary Sewer Extension

Project Update: Oct 6, 2017

    

 

 

Building

:
Today the installation of the roof panels began.  Weather dependent, the building should be enclosed by early November as per the original schedule.

Next week the permanent Electrical service is scheduled to be energized 


River Valley Rd Sanitary Extension and Access Rd to Building

:
The contractor is finishing up the Sanitary Sewer and will begin the storm sewer installation and access road grading next week.


Roof
The Westerly drive into the church has been closed to church traffic and is being used for construction traffic. 


Contact Information:
Building:
Katie Jelacic, P.E.
Project Engineer
262-524-3587
262-349-6511 (c)
kjelacic@waukesha-wi.gov

Sewer Extension:
Chris Langemak, P.E.
Project Engineer
262-524-3598
262-349-6512 (c)

P3